Status of the ESS Elliptical Cryomodules at CEA Saclay
May, 2017
3 pages
Contribution to:
- Published: May, 2017
Report number:
- IPAC-2017-MOPVA040
View in:
Citations per year
Abstract: (JACoW)
The first ESS prototype cryomodule with medium beta cavities named M-ECCTD is being assembled at CEA Saclay. The Q curves of the 4 cavities mounted inside the cryomodule are presented, and the four power couplers have been conditioned at high power before their assembly onto the cavity string. Completion of the M-ECCTD assembly outside clean room is in progress as well as the finalization of the RF power test stand preparation. RF power tests of the M-ECCTD will be performed during summer 2017. CEA is preparing the production of the ESS medium and high beta cryomodules of the series before the test of the M-ECCTD and the contracts for the procurement of the most critical components have already been signed- cryomodule
- cavity
- cryogenics
- vacuum
- SRF
References(8)
Figures(0)
- [1]
- [2]
- [3]
- [4]
- [5]
- [6]
- [7]
- [8]