Beam Commissioning Results of the CSNS Linac

May, 2017
3 pages
Contribution to:
  • Published: May, 2017

Citations per year

201820202022202420243012
Abstract: (JACoW)
The China Spallation Neutron Source(CSNS) accelera-tor systems is designed to deliver a 1.6GeV, 100kW pro-ton beam to a solid metal target for neutron scattering research. It consists of a 50keV H⁻ Ion Source, a 3MeV Radio Frequency Quadrupole (RFQ), an 80MeV Drift Tube Linac (DTL), and a 1.6GeV Rapid-cycling Synchro-tron (RCS). The beam commissioning has been started since April 2015. The Front End and three of the four DTL tanks have been commissioned, while the last tank and the RCS will be commissioned at the autumn this year. At the end of the DTL3, beam has been accelerated to 61MeV with nearly 100% transmission, other parame-ters such as peak current, transverse emittance and beam orbit have reached the design goal. Results and status of the beam commissioning program will be presented.
  • DTL
  • linac
  • rfq
  • cavity
  • quadrupole